Over the last few weeks the slipway work has been moving on well. All the large piles are now in place and the first of the smaller piles to hold the toe of the slipway have been installed.
Ashore the contractors have been assembling the slipway sections and lowering them in to place. Very quickly the slipway has started to take shape. Its nowhere near finished but you get a good idea of how its going to look. The angle of the slipway is the same as it was for our Mersey but the shape of the slipway is very different to match the underwater profile of the Shannon.
Work on the boathouse is coming on well too. Electricians are busily working away as are carpenters, plasterers and window fitters.
The photos above are from the crew room above the ILB shed.